"In government, nothing is easy," Town Manager Robert Smith told the West Orange Times & Observer this spring, while explaining why a trail of less than a mile took close to a decade to start.
The new bridge over the canal between Lake Down and Lake Butler is the part most of Windermere has seen. It sits where South Lake Butler Boulevard meets Dirt Main Street. It now has a name, Centennial Bridge, and as of late October it has signs. The bridge is the newest part of the project. The ground under it has a much longer history, and that history explains why the Ward Trail runs where it does.
A Railroad Line Windermere Let Go
The trail follows an old railroad right-of-way. When CSX Transportation left that corridor more than 50 years ago, the Town didn't buy it. Mayor Andy Williams told the Observer that Windermere may not have had the money at the time. Several private owners bought pieces instead. Ken and Susan Ward bought most of it, the stretch from 12th Avenue to Windermere Road, and placed it in a trust.
Smith was hired in 2011, and buying that right-of-way back was one of the first tasks on his list. Before negotiating, the Town had Kimley-Horn study the area's roads and sidewalks in 2015. Talks with the Wards stalled for years. In 2017 the trust passed to the family's sons, who accepted the Town's appraisal. Windermere Town Council finalized the purchase on March 13, 2018. Williams was sworn in as a council member at that same meeting. The Town got the rest of the corridor through property swaps, and the trail carries the Ward name.
That sequence explains why the trail sits where it does. It runs on an old rail line because that line was the one continuous strip of land through this part of town that could be put back together.
Fourteen Feet, Two Golf Carts
The old pedestrian crossing at this canal was narrow and steep. Williams told the Observer it looked the same when he rode it to Windermere Elementary in the 1980s. Bikes went up it one at a time. Golf carts didn't fit at all, so drivers heading downtown used the road bridge.
The replacement is a railroad-style bridge, which fits the corridor's history.
| Previous pedestrian bridge | Centennial Bridge | |
|---|---|---|
| Bikes | Single file, steep approach | Built for shared bike and foot traffic |
| Golf carts | Not enough room; carts used the road bridge | 14 feet wide, so two carts can pass |
| Height | Not reported | 8 feet |
The golf-cart width is what changes how people use it. Smith told the Observer the main reason for the wider bridge was to connect old downtown Windermere with the newer parts of town. Residents north of the canal get direct access to parks, boat ramps and the Town's civic centers without using the road bridge. School-morning safety was the other reason. With room for golf carts, the crossing now serves trips to the parks and civic buildings as well as the school run.
The Town opened portions of the trail and the bridge on August 6, in time for the new school year. The project includes a shared-use trail, the bridge, drainage improvements and new plantings along roughly half a mile. The bridge is open to pedestrians, cyclists and golf carts, and the Town said crews would keep working through the fall on the remaining pathway sections and plantings. "The Ward Trail and Pedestrian Bridge is an investment in Windermere's future," Williams said in the Town's announcement.
Golf carts on the trail are covered by the Town's own rules. The Town of Windermere golf cart page says carts that can't go faster than 20 mph may use roads designated for golf carts with posted limits of 30 mph or less. They aren't titled or registered. Drivers must be at least 18 or hold a valid driver's license or learner's permit. Low-speed vehicles, which can go above 20 mph but no more than 25, must be registered, titled and insured. This is general information, not legal advice, so please check the Town's page or ask the Town directly about your own cart before you drive it.
Who Paid for the Crossing
Getting the land was the first hurdle. Paying to build on it took several funding sources, plus a local foundation:
- Federal: a $760,000 appropriation through the Safe Routes to School program for Phase 1 and the bridge, signed into law on March 14, 2022, according to the Town's Ward Trail project page.
- State: $1 million approved by the Florida Legislature in 2023.
- ARPA funds: listed with the federal and state money in a May 2024 West Orange Times & Observer project update. That report estimated construction at about $2,002,828, plus $120,170 for construction engineering and inspection.
- Healthy West Orange: a $100,000 reimbursement grant from the Foundation for a Healthier West Orange for plantings and grounds work around the bridge and trail. Staff put it before Council in the October 13, 2026 agenda with a recommendation to approve.
That last grant also affects what will stand at the bridge. Under the agreement, Healthy West Orange gets permanent recognition. Staff proposed one double-sided sign near the Centennial Bridge so trail users see it coming and going.
What's Going in the Ground
Before paving started, Town staff and the Windermere Tree Board walked the corridor in February to decide which trees to keep. The plan removes nearly 70 existing trees and adds more than 100. The planting list includes longleaf pines, firebush, saw palmettos and sabal palms. Benches and lighting are also planned along the path.
Parents who ride to school told the Observer the paved trail will also keep bikes off the sandy paths that have thrown riders, including children.
How the Bridge Got Its Name
At its September 8 meeting, Town Council voted 5-0 to rename the new pedestrian bridge Centennial Bridge. Council Member Allen made the motion and pointed out that a logo had already been designed for the Town's Centennial celebrations. So the trail is named for the family that held the land, and the bridge is named for the Town that bought it back. Crews installed signs along the Ward Trail and Centennial Bridge on Tuesday, October 27.
The Town's October packet expects the project to be complete by December 2026. In August the Town said it plans a full grand opening this fall or winter and will post details on its website and social media.
The Rest of the Corridor
The bridge is part of Phase 1, the first of four phases. According to the Observer, the later phases are:
- Phase 2: North Drive to Sixth Avenue
- Phase 3: along Sixth Avenue, from Main Street to Apopka-Vineland Road
- Phase 4: Chase Road/12th Avenue to Sixth Avenue
Smith said he would like Phase 2 finished within five years, but that depends on funding and on property tax reform. Phase 1 took from a 2018 land purchase to a partial opening in 2026. Each later phase runs toward Sixth Avenue and Main Street, so how fast the rest gets built decides how much of the old rail line becomes one continuous route into downtown.
Two Town events this month are close to the downtown end of the route. The Holiday Extravaganza Art Show runs November 14 and 15, 10 a.m. to 5 p.m., at Town Hall, 520 Main St. The WPD Foundation's Light Up Windermere food truck night fills Windermere Town Square on November 20 from 5:30 to 9:30 p.m., according to the Town's events calendar.
A bridge two golf carts can share changes how the north side of town reaches Main Street, and that matters when you weigh a home on either side of the canal. If you're thinking about what your home is worth in Windermere, Pamela Porazzo can show you how location relative to the Ward Trail and downtown plays into it. Get Your Home Valuation, and let's talk it through.